In line with Australia’s commitment to reduce carbon
emissions and move towards renewable energy, Snowy
2.0 is a major project estimated to cost in the region of
A$5.2 billion.
Early feasibility studies investigated the viability of a
tunnel linking Lake Talbingo and Lake Tantangara.
Situated underground, along the tunnel would be the
power station housing six turbines capable of generating
2000 megawatts. Power generation is not expected until
2025.
The initial site investigation by SMEC and GHD led to
HMA Geotechnical being awarded the instrumentation
installation work.
HMA Geotechnical began installation work in November
2017 and completed the work in February 2021
Construction of Keepit Dam began in the late 1930’s but
was delayed during WW2. Work was restarted after the war
and only reached completion in 1960.
The mass concrete main dam and several rock-filled
saddle dams give a storage capacity of 425000 megalitres.
Keepit Dam has undergone recent upgrades, the most
recent was to strengthen the concrete structure using post
tensioned cables.
This work would ensure potential overturning effects
during flood and/or earthquake events would be mitigated
HMA Geotechnical was contracted to supply large
diameter Vibrating Wire load cells and logging systems
to monitor the tensioning of the reinforcing cables and
thereby the load in kN.
To relieve traffic pressure on the existing Harbour Bridge
and Tunnel, the NSW Government sought expressions of
interest to build a second tunnel to the Western side of the
harbour in July 2020.
In June 2021, NSW 2021-2022 budget allocated $6.3
billion over the next four years for the Western Harbor link
to go ahead.
In Dec 2021the geotechnical investigation was awarded to
GHD and SMEC.
HMA Geotechnical was selected to provide the
instruments and installation equipment for boreholes in
nine locations.
Site work commenced mid-February 2022
At 287 giga litres Cardinia Reservoir is Melbourne Water’s
second largest reservoir. Constructed in the early 1970’s
it has no direct catchment, instead water is fed via Silvan
Reservoir and more recently the Victorian Desalination
Plant.
With recent improvements in dam safety and design
standards Cardinia Dam has slipped below best practice
guidelines in dam safety.
The upgrade to Cardinia dam will bring the fifty-year-old
structure back into compliance with the guidelines issued
by the Australian National Committee on Large Dams.
(ANCOLD)
Melbourne Water has a duty of care to comply under the
Water Act 1989 for all dams within its portfolio.
The upgrade works are due to start in 2024/25 and
expected completion is mid 2025
Located in the Latrobe Valley, Victoria, Australia.
Hazelwood Power station was constructed during the mid
to late 1960’s and supplied Victoria with up to 25% of its
power.
The brown coal fuel for the eight 200MW turbines was
mined from the adjoining pit.
In 2005 the World Wildlife Fund reported that Hazelwood
power station was one of the world’s most polluting,
emitting 3% of Australia’s annual greenhouse gas
emissions.
In 2016, Engie, the joint owner, announced the power
station and mine would close and in March 2017 it finally
closed.
The power station was demolished in November 2020.
The 1,281hectare mine presented another problem.
The plan is to allow the void to fill with
Constructed in 1957 Upper Yarra dam is located 23km
Northeast of Warburton, Victoria.
In 2017 Melbourne Water announced that upgrades of the
dam wall and surrounds were necessary.
In 2019 the first stage of upgrades began with the second
stage commencing in 2020.
HMA Geotechnical became involved with the upgrades
mostly through improved logging equipment, Instrument
cable extensions and Weir monitor calibrations.
Re-routing instrument cables and preserving them during
construction was a major undertaking.
Grange Resources operates Savage River Mine which lies
100km Southwest of Burnie in Tasmania.
The magnetite ore body stretches 25km south of the
Savage River township ranging in thickness from 40m
to 150m. Current production is two million tonnes of
premium iron ore pellets; this is expected to rise to
nearly three million tonnes as the open cut mine extends
underground.
HMA Geotechnical was contracted to install vibrating
wire piezometers both in the open cut pit and the newly
opened underground drive.